Construction Update - July 2011:

Plumbing fixture - new Teacher's Lounge bathroom.

Removing existing unit ventilator.

VRF heating & cooling system line kits.

Display case vestibule.

EIFS installation - Administration Addition

Installing metal decking - Classroom Addition.

New boilers & loop water pumps.

New reception office.

New through wall sleeve for change air units.
Construction Update - May 2011

Structural Steel Erection for Alma music room - operable partitioning.

Steel Joint Installation - Alma music room.

Installing metal decking and delivering structural steel - Alma music room.

In-wall plumbing rough-in utility closet - Alma classroom addition.

Alma addition fluid membrane installation.

Alma addition fluid membrane installation.

Alma addition concrete installation for canopy columns.

CMU being installed at Alma classroom addition.

Alma classroom addition exterior view - West elevation.

Brick installation at Alma music room - South elevation.

Alma sample wall mock-up brick installation.

Alma classroom addition - street view.

Alma classroom addition - North elevation.

Alma classroom addition - exterior view West elevation.

Alma administration addition - exterior.

Alma administration addition - exterior view West elevation.

New entrance, office, and classrooms structure nearly complete

Classroom additions structure
Work Continues

Site specific Bond Issue sign.

New tapered system being installed.

Fast 100 Adhesive applied in preparation for tapered insulation system.

New tapered insulation being installed.
Removal of existing roof system and lightweight deck. This reveals deterioration at the deck's edge due to poor roofing system.

Removal of existing roof system. New roofing base sheet applied.

Roof Replacement - Summer 2010
Demolition of overhang. This is where the new addition will tie-in to the existing school building.

Classroom Addition - Winter/Spring 2011
Sewer line installation.

Rebar/footing installation for administration addition.

Footing installation - new teacher's lounge restroom.

Footing installation.

Plumbing rough end - new teacher's lounge restroom.